Question 212

Which of the following is the formal acceptance of the project?

    Correct Answer: B

    The formal acceptance of a project is known as a sign-off. This is when project stakeholders officially approve the project deliverables and outcomes, indicating that the project has met its objectives and is complete. A project review, risk assessment, and inspection trend analysis are important activities in project management, but they do not constitute formal acceptance of the project.

Discussion
OctavianGOption: B

Business analysts are responsible for obtaining stakeholder approvals and are required to understand who holds decision-making responsibility and who possesses authority for sign-off across the initiative.

OctavianG

Project sign-off is one of the many activities you'll do at the end of a project. This is the phase where you've handed over all deliverables and are about to dismiss the project team. The typical steps in this phase include: Project sign-off and completion of all other legal formalities.