Question 51

Which stakeholder must approve the business analysis approach to ensure that the business analysis approach is compatible with the other project activities?

    Correct Answer: B

    The project manager must approve the business analysis approach to ensure that it is compatible with the other project activities. This is because the project manager is responsible for the overall planning and coordination of the project, ensuring that all aspects, including the business analysis, are aligned and appropriately integrated into the project plan.

Discussion
Wlkkkk

BABOK v3 p30

Farooq_95Option: B

B is correct as per BABOK v3 Section 3.1.7