CBAP Exam QuestionsBrowse all questions from this exam

CBAP Exam - Question 51


Which stakeholder must approve the business analysis approach to ensure that the business analysis approach is compatible with the other project activities?

Show Answer
Correct Answer: B

The project manager must approve the business analysis approach to ensure that it is compatible with the other project activities. This is because the project manager is responsible for the overall planning and coordination of the project, ensuring that all aspects, including the business analysis, are aligned and appropriately integrated into the project plan.

Discussion

2 comments
Sign in to comment
Wlkkkk
Nov 16, 2022

BABOK v3 p30

Farooq_95Option: B
Feb 23, 2024

B is correct as per BABOK v3 Section 3.1.7