CBAP Exam - Question 265


In a software implementation project, the designated business analyst (BA) has conducted all the elicitation activities and now needs to confirm the elicitation results.

What is used by the BA Professional to guide which sources of information and which results are to be compared?

Show Answer
Correct Answer: BC

To confirm the elicitation results in a software implementation project, the business analyst uses the Elicitation Activity Plan. This plan is specifically designed to guide which sources of information and which elicitation results are to be compared. It details the methods and procedures followed during the elicitation activities, thus providing a clear framework for validating the outcomes. The plan ensures that the elicitation process is thorough and that all relevant information is accurately captured and assessed.

Discussion

10 comments
Sign in to comment
siliconvalleykamOption: C
Jan 13, 2021

C. Elicitation activity plan

rhsdeal
Apr 12, 2021

Ans C. BABOK v3, 4.3.5 Confirm Elicitation Results: Guidelines and Tools pg. 67: • Elicitation Activity Plan: used to guide which alternative sources and which elicitation results are to be compared.

Exam_Masters
Jan 23, 2022

Ans C. Page 77

km_45Option: C
Jan 16, 2021

C - BABOK v3, 4.3.5

[Removed]Option: C
Aug 29, 2023

C - The Elicitation Activity Plan is Guidelines for this task

SunlordOption: C
Jan 2, 2022

Answer is C as per BABOK V3 Pg. 66 "Inconsistencies in elicitation results are often uncovered when business analysts develop specifications and models. These models may be developed during an elicitation activity to improve collaboration"

Pank_HDOption: C
Apr 26, 2022

• Elicitation Activity Plan: used to guide which alternative sources and which elicitation results are to be compared

Sha7rourOption: C
Sep 9, 2022

C seems to be the answer

Anjx25_Option: C
Mar 12, 2023

Agree with C asper Babok page 67 4.3.5

Jules_CmrfrdOption: C
Nov 8, 2023

C - The Elicitation Activity Plan is a guideline for the task

NorieRoseOption: C
Jan 30, 2024

Elicitation Activity Plan - BABOK v3, 4.3.5

RabbitsfootOption: B
Mar 16, 2024

While options such as the information management approach (Option A), elicitation activity plan (Option C), and business analysis approach (Option D) are important aspects of business analysis, the business analysis plan specifically provides guidance on how to confirm elicitation results and ensures alignment with the overall project objectives. Therefore, Option B is the most appropriate choice in this scenario.

Rabbitsfoot
Apr 1, 2024

No, changing my answer to C