Question 265

In a software implementation project, the designated business analyst (BA) has conducted all the elicitation activities and now needs to confirm the elicitation results.

What is used by the BA Professional to guide which sources of information and which results are to be compared?

    Correct Answer: C

    To confirm the elicitation results in a software implementation project, the business analyst uses the Elicitation Activity Plan. This plan is specifically designed to guide which sources of information and which elicitation results are to be compared. It details the methods and procedures followed during the elicitation activities, thus providing a clear framework for validating the outcomes. The plan ensures that the elicitation process is thorough and that all relevant information is accurately captured and assessed.

Discussion
siliconvalleykamOption: C

C. Elicitation activity plan

rhsdeal

Ans C. BABOK v3, 4.3.5 Confirm Elicitation Results: Guidelines and Tools pg. 67: • Elicitation Activity Plan: used to guide which alternative sources and which elicitation results are to be compared.

Exam_Masters

Ans C. Page 77

km_45Option: C

C - BABOK v3, 4.3.5

[Removed]Option: C

C - The Elicitation Activity Plan is Guidelines for this task

RabbitsfootOption: B

While options such as the information management approach (Option A), elicitation activity plan (Option C), and business analysis approach (Option D) are important aspects of business analysis, the business analysis plan specifically provides guidance on how to confirm elicitation results and ensures alignment with the overall project objectives. Therefore, Option B is the most appropriate choice in this scenario.

Rabbitsfoot

No, changing my answer to C

NorieRoseOption: C

Elicitation Activity Plan - BABOK v3, 4.3.5

Jules_CmrfrdOption: C

C - The Elicitation Activity Plan is a guideline for the task

Anjx25_Option: C

Agree with C asper Babok page 67 4.3.5

Sha7rourOption: C

C seems to be the answer

Pank_HDOption: C

• Elicitation Activity Plan: used to guide which alternative sources and which elicitation results are to be compared

SunlordOption: C

Answer is C as per BABOK V3 Pg. 66 "Inconsistencies in elicitation results are often uncovered when business analysts develop specifications and models. These models may be developed during an elicitation activity to improve collaboration"