ECBA Exam QuestionsBrowse all questions from this exam

ECBA Exam - Question 19


Which of the following activities are performed during the requirements life cycle management phase?

Show Answer
Correct Answer: A,C

During the requirements life cycle management phase, one of the primary activities performed is to trace requirements. This involves analyzing and maintaining the relationships between requirements, designs, and solution components for impact analysis, coverage, and allocation. Other tasks like eliciting requirements and prioritizing designs do not fall under this phase, as elicitation is typically performed earlier in the requirements gathering phase, and prioritization is usually related to requirements rather than designs.

Discussion

13 comments
Sign in to comment
Throneroom
Oct 5, 2022

I think this question means which tasks are NOT performed in the Requirements and Life Cycle Management Tasks.

INDEAVROption: C
Oct 19, 2022

I think the correct answer is "Trace Requirements" as the other ones I would classify as misleading - e.g. it's requirements prioritization, not design prioritization.

HazemnzOption: C
Jan 7, 2023

BABOK page 76

m4tim4tiOption: C
Feb 26, 2023

BABOK p. 76 The Requirements Life Cycle Management knowledge area includes the following tasks: • Trace Requirements: analyzes and maintains the relationships between requirements, designs, solution components, and other work products for impact analysis, coverage, and allocation.

Adnan8t2Option: C
May 1, 2023

ANSWER: C Page 76 – BABOK V3 The Requirements Life Cycle Management knowledge area includes the following tasks: • Trace Requirements: analyzes and maintains the relationships between requirements, designs, solution components, and other work products for impact analysis, coverage, and allocation.

HazemnzOption: C
Jan 7, 2023

BABOK page 93

A_peOption: C
Feb 11, 2023

I think Trace requirements is correct

amrita0204Option: C
Mar 17, 2023

I think it should be option C

muf33f3Option: B
May 30, 2023

All answers are correct except Elicitat Requirements. I agree with @Throneroom's comment

Sourabh_SharmaOption: A
Sep 13, 2023

Question seems to be incorrect, Elicit requirement is not part of RLCM rest all activities are performed during RLCM. Correct question should be which activity is “NOT” part of RLCM.

Only12goOption: C
Sep 16, 2023

Answer is C - The knowledge area of requirements life cycle management involves five tasks that a business analyst needs to perform: trace requirements, maintain requirements, prioritise requirements, asses requirements changes, and approve requirements.

OlutimiOption: C
Dec 12, 2023

Answer is C; Trace requirement. The other tasks are maintain, prioritize, assess and approve.

25a199bOption: C
Jun 26, 2024

C- page 76