Which of the following activities are performed during the requirements life cycle management phase?
Which of the following activities are performed during the requirements life cycle management phase?
During the requirements life cycle management phase, one of the primary activities performed is to trace requirements. This involves analyzing and maintaining the relationships between requirements, designs, and solution components for impact analysis, coverage, and allocation. Other tasks like eliciting requirements and prioritizing designs do not fall under this phase, as elicitation is typically performed earlier in the requirements gathering phase, and prioritization is usually related to requirements rather than designs.
I think this question means which tasks are NOT performed in the Requirements and Life Cycle Management Tasks.
I think the correct answer is "Trace Requirements" as the other ones I would classify as misleading - e.g. it's requirements prioritization, not design prioritization.
BABOK page 76
BABOK p. 76 The Requirements Life Cycle Management knowledge area includes the following tasks: • Trace Requirements: analyzes and maintains the relationships between requirements, designs, solution components, and other work products for impact analysis, coverage, and allocation.
ANSWER: C Page 76 – BABOK V3 The Requirements Life Cycle Management knowledge area includes the following tasks: • Trace Requirements: analyzes and maintains the relationships between requirements, designs, solution components, and other work products for impact analysis, coverage, and allocation.
BABOK page 93
I think Trace requirements is correct
I think it should be option C
All answers are correct except Elicitat Requirements. I agree with @Throneroom's comment
Question seems to be incorrect, Elicit requirement is not part of RLCM rest all activities are performed during RLCM. Correct question should be which activity is “NOT” part of RLCM.
Answer is C - The knowledge area of requirements life cycle management involves five tasks that a business analyst needs to perform: trace requirements, maintain requirements, prioritise requirements, asses requirements changes, and approve requirements.
Answer is C; Trace requirement. The other tasks are maintain, prioritize, assess and approve.
C- page 76