Question 115

You are the business analyst for THY Organization and you have gathered the requirements. You have presented the requirements to the stakeholders and they have approved your requirements.

You are now working with Francie on recording the dependencies and relationships for each of the requirements.

Why would you want to record the dependencies and relationships for the requirements?

    Correct Answer: A

    Recording the dependencies and relationships for the requirements helps to determine the sequence in which requirements are to be addressed. By understanding these dependencies, one can prioritize and schedule the implementation of requirements effectively, ensuring a smooth and logical progression of tasks. This minimizes risks of delays and inefficiencies that could arise from a disorganized or haphazard approach.

Discussion
Farooq_95Option: A

A is correct because the sequence in which requirements need to be addressed is important to work upon. If this sequence is missing, the requirements will be implemented in a haphazard manner leading to time delays and failures.