Question 13

Henry and Fred are working together on business analysis duties for the implementation of new software. Henry, the business analyst, tells Fred that they should take the current measurement of productivity, and then measure again after the solution has been implemented. This benchmarking approach will allow Henry and

Fred to see the real effect of the solution on the business need. What term is assigned to this measurement?

    Correct Answer:

Discussion
JennKOHOption: C

C. Key performance indicators

Stella9711Option: C

Key performance indicators

OZMagsOption: C

Correct answer is C