Which of the following is a visual decomposition of the project scope?
Which of the following is a visual decomposition of the project scope?
A visual decomposition of the project scope is the Work Breakdown Structure (WBS). The WBS breaks down the entire project into smaller, more manageable parts called work packages. This hierarchical decomposition helps in planning, organizing, and controlling the scope of the project.
a,b,c - incorrect therefore, d - correct
WBS is also called as a Project scope breakdown.
Work Breakdown Structure (WBS) is correct. As per BABOK v3, 10.22.3.2, Work to be Done: this decomposition (known as a Work Breakdown Structure or WBS) breaks endeavors into phases, milestones, work activities, tasks, work items, and deliverables.