Question 70

You are the business analyst for your organization and you are completing the manage requirements traceability process. You are tracking the requirements to determine how the requirements are interrelated with one another and with the actual delivery of the project scope.

There are actually three reasons why the business analyst should trace requirements.

Which one of the following is not one of the three reasons why trace requirements is useful?

    Correct Answer: D

    Managing requirements traceability involves analyzing and maintaining relationships between requirements, designs, solution components, and other work products for impact analysis, requirements coverage, and requirements allocation. Quality control is not directly associated with the traceability of requirements but rather with ensuring the quality of the project deliverables, making it the correct answer.

Discussion
HappyAOption: D

Ans is D as per pg 76

NickMane

correct

eeghoOption: D

Trace Requirements: analyzes and maintains the relationships between requirements, designs, solution components, and other work products for impact analysis, coverage, and allocation.

HangMBOption: D

Trace Requirements: analyzes and maintains the relationships between requirements, designs, solution components, and other work products for impact analysis, coverage, and allocation. (page 76)

SaintTCOption: D

ans is D - Babok v3 5.1.2.

RfcuencaOption: D

Option D Babok v2 - pages 68, 69