You are the business analyst for your organization. You are coaching Tom about the different approaches to business analysis.

Which type of business analysis approach has the most business analysis work at the beginning of the project or during the start of a project phase?

Show Answer
Correct Answer: C

The plan-driven approach, also known as the predictive approach, tends to have the most business analysis work at the beginning of the project or during the start of a project phase. This approach focuses on detailed planning and documentation before any actual project execution starts. Requirements and specifications are gathered extensively at the initial stages, which helps to create a solid plan for the entire project.

Discussion

2 comments
Sign in to comment
rmr29Option: C
Oct 12, 2023

Plan-driven(V2) = predictive (V3)

RfcuencaOption: C
Jan 16, 2024

Option C Babok v2 page 20