What element of the conduct elicitation activity is tracked to provide a basis for future planning?
What element of the conduct elicitation activity is tracked to provide a basis for future planning?
Time actually spent eliciting the requirements is tracked to provide a basis for future planning. This information helps in estimating the effort required for similar future activities and in improving the accuracy of project timelines and resource planning.
Babok v2. A is the correct answer.
Agree Makes sense