Exam CBAP All QuestionsBrowse all questions from this exam
Question 153

You are the business analyst for your organization and preparing to complete the requirements elicitation activities. Your manager wants to know when the requirements elicitation process will be completed.

Which of the following responses best describes the nature of the requirements elicitation process?

    Correct Answer: D

    Eliciting requirements is not a compartmentalized activity. It is an ongoing process that occurs throughout the duration of the project as business analysis work continues. This means it cannot be confined to a specific schedule, project size, or stakeholder willingness. Requirements may evolve and change as more information becomes available or as project conditions change, making the requirements elicitation process continuous rather than limited to a set timeframe.

Discussion
cc2104Option: D

4.0 Elicitation and collaboration work is never a 'phase' in business analysis; rather, it is ongoing as long as business analysis work is occurring. Eliciting business analysis information is not an isolated activity.

FedaraOption: D

Elicitation and collaboration work is never a 'phase' in business analysis; rather, it is ongoing as long as business analysis work is occurring. BABOK v3, pg 53

FedaraOption: D

There is no start and stop date

NickManeOption: B

B is also good answer

binu801Option: B

Can anyone explain why D is the answer. For me the answer should be B

Farooq_95Option: D

Correct answer is D. As per BABOK v3 pg 53, Elicitation and collaboration work is never a 'phase' in business analysis; rather, it is ongoing as long as business analysis work is occurring. Elicitation and collaboration can be planned, unplanned, or both.

TyphatOption: D

Elicitation activity is not phased. Rather it can occur at any point during the project

nitin_ricoOption: D

IF THERE IS NO LIMIT THEN HOW pm WILL KNOW WHEN A REQUIRMENT ELICITATION WILL BE OVER ? HERE i AM ASSUMING REQ. ELICITATION WORK FOR SPECIFIC CONTEXT? OTHER WISE IT WILL KEEP GOING

CBAP_ExamOption: D

No option B cannot be the right one. As keeping stakeholders interest at business analysis activities is one of the primary roles of a Business Analyst. For me option D is correct.

timojeagaOption: C

The answer looks more like C. The side of the project, determines the duration of the requirement elicitation since the PM wants to know how long it will take for the process to be completed