Which of the following is the process of analyzing the areas of a project that are most affected by risk?
Which of the following is the process of analyzing the areas of a project that are most affected by risk?
Risk analysis is the process of identifying and evaluating the areas of a project that are most affected by risk. This involves assessing the likelihood and impact of different risks, hence determining which areas require the most attention and mitigation efforts. Risk categorization involves grouping risks into categories, but does not specifically focus on the areas most affected by risk.
D - There is no risk categorization in the BABOK. Categorization infers grouping risk types, not managing areas most affected by risk. The BABOK there is only risk analysis and analyze is a key word in the question.
Considering babok v3, only risk analysis is appropriate