Question 217

The ____, an output of the define scope process, does document the process and criteria for accepting completed products.

    Correct Answer: C

    The project scope statement, an output of the define scope process, documents the process and criteria for accepting completed products. The project scope statement provides a detailed description of the project deliverables and the work required to create those deliverables, including the criteria that must be met for the deliverables to be accepted.

Discussion
RabbitsfootOption: C

BABOK V3 Glossary - project scope: The work that must be performed to deliver a product, service, or result with the specified features and functions. A 'statement' of the project scope would answer the question.