The ____, an output of the define scope process, does document the process and criteria for accepting completed products.
The ____, an output of the define scope process, does document the process and criteria for accepting completed products.
The project scope statement, an output of the define scope process, documents the process and criteria for accepting completed products. The project scope statement provides a detailed description of the project deliverables and the work required to create those deliverables, including the criteria that must be met for the deliverables to be accepted.
BABOK V3 Glossary - project scope: The work that must be performed to deliver a product, service, or result with the specified features and functions. A 'statement' of the project scope would answer the question.