Question 394

The project manager wants to have the requirements analysis phase approved and asks the business analyst (BA) if this is possible. The BA wants to ensure that the requirements package is complete prior to closing the analysis phase. What would help the BA expedite the approval process for the analysis phase?

    Correct Answer: B

    To expedite the approval process for the analysis phase, the business analyst should focus on the business analysis information architecture. This is because the architecture helps ensure that the complete set of requirements is properly organized and related. It defines and verifies the relationships among various types of business analysis information, such as requirements, designs, and elicitation results, ensuring the requirements package is comprehensive and cohesive. This thoroughness helps facilitate stakeholder understanding and decision-making, thereby speeding up the approval process.

Discussion
DoomsdayNairOption: D

D. Business analysis approach

QualmsOption: B

The question is from RADD. Answer is Option B - BA Information Architecture. BABOK 7.4.4.5 says " it describes how all of the business analysis information for a change relates. It defines relationships for types of information such as requirements, designs, types of models, and elicitation results. Understanding this type of information structure helps to ensure that the full set of requirements is complete by verifying the relationships are complete."

rhsdeal

From Question: "The BA wants to ensure that the requirements package 'is complete' prior to closing the analysis phase." BABOK V-3 7.4.4.5 Business Analysis Information Architecture pg.151 (...) helps to ensure that the 'full set of requirements is complete' by verifying the relationships are complete.

RabbitsfootOption: B

Focusing on business analysis information architecture can help expedite the approval process for the analysis phase by ensuring that the requirements package is complete and well-structured, facilitating stakeholder understanding and decision-making. None of the other options can help with expediting approvals.

JoseyOption: B

The answer is B

mdadewaleOption: B

BABOK V-3 7.4.4.5