Question 42

What is a risk that business analysts (BAs) look for when managing stakeholder engagement?

    Correct Answer: B

    Business analysts (BAs) manage stakeholder engagement and monitor various risks associated with it. One significant risk is delayed approvals, which can hinder project progress. This is because stakeholder engagement typically involves obtaining feedback, decisions, and approvals at various stages. If these approvals are delayed, it can lead to project delays and increased costs.

Discussion
HazemnzOption: B

BABOK page 73

Adnan8t2Option: B

73 Business analysts continually monitor for such risks as: • stakeholders being diverted to other work, • elicitation activities not providing the quality of business analysis information required, and • delayed approvals.