Question 118

The RGQ Organization utilizes a change log.

What is a change log?

    Correct Answer: D

    A change log is a document that tracks the changes that have been received, including their implementation to the project solution. This includes all details of changes, their status, and their impacts on the project. It ensures proper documentation and helps in tracking the progress and effects of the changes over time.

Discussion
animalstartupOption: D

Based on BABOK v2, Page 21, it stated that "a change log that tracks the changes that have been received, and an analysis of the impact of the change not only to the project, but also to other business and automated systems." It should be option D