CBAP Exam QuestionsBrowse all questions from this exam

CBAP Exam - Question 278


A business analyst (BA) has been coordinating several meetings with stakeholders to reach consensus regarding the solution design to implement a global currency exchange system for an international bank. Consensus has not been reached yet, although BA has great communication skills and is trusted by all stakeholders. The stakeholders formally approved the business need initially.

Why is there disagreement?

Show Answer
Correct Answer: A

The explanation behind the disagreement in this scenario is that the requirements are interpreted differently by each stakeholder. When stakeholders have varied interpretations of the requirements, it leads to different perspectives and priorities, which can prevent consensus from being reached. This is consistent with the common challenge in project management where conflicting values and understandings of requirements among stakeholders cause disagreements, even if the stakeholders initially approved the business need.

Discussion

5 comments
Sign in to comment
[Removed]Option: A
Jun 10, 2021

Answer is A. Pg 96 A conflict may arise among stakeholders as a result of different interpretations of requirements or designs and conflicting values placed on them.

cc2104Option: A
Aug 17, 2021

Ans A. 5.5.4.2 Stakeholder groups frequently have varying points of view and conflicting priorities. A conflict may arise among stakeholders as a result of different interpretations of requirements or designs and conflicting values placed on them. The business analyst facilitates communication between stakeholders in areas of conflict so that each group has an improved appreciation for the needs of the others.

HappyAOption: A
Feb 1, 2021

Pg68 Ans is A

JerryMag4Option: C
Dec 29, 2023

C. The approval authority for the solution is unclear. 5.5.4.3. Business analysts are responsible for ensuring that the stakeholders with approval authority understand and accept the requirements. Key words in the question, "Consensus"

Farooq_95
Apr 25, 2024

C is not correct. This is because approval authority may be unclear but this is likely to cause delays in approval but does not lead to disagreement among the stakeholders.

Farooq_95Option: A
Apr 25, 2024

Disagreements (or conflicts) may arise among stakeholders as a result of different interpretations of requirements or designs and conflicting values placed on them. (BABOK v3 5.5.4.2)