Question 427

A business analyst (BA) assigned to a project has been asked to implement regulatory requirements based on priority. What type of traceability relationship can the BA use to find all the solution components that need to be implemented?

    Correct Answer: B

    To identify the necessary solution components to implement regulatory requirements, the appropriate traceability relationship is 'Satisfy'. This relationship connects the requirements to the solution components that fulfill them. For example, it links a functional requirement to the solution component that meets this requirement, ensuring that all parts of the solution are implemented to meet the regulatory standards.

Discussion
siliconvalleykamOption: B

I think this is Satisfy

OlivierPaudexOption: B

Satisfy - relation between an element and the requirements it is satisfying Depends - relation between 2 requirements We are talking here relations between requirements and solution components which should be satisfying.

rupakarthikOption: B

Satisfy: relationship between an implementation element and the requirements it is satisfying. For example, the relationship between a functional requirement and a solution component that is implementing it.

Kajol_2021Option: B

B - relationship between an implementation element and the requirements it is satisfying

DoomsdayNairOption: D

D. Dependency

DoomsdayNair

Key Word: Find

MFZZOption: D

D is correct. Requirements which depend on each other need to be implemented together, therefore they should be at the top of the backlog.

cc2104Option: B

5.1.4.2 Satisfy: relationship between an implementation element and the requirements it is satisfying. For example, the relationship between a functional requirement and a solution component that is implementing it.

RabbitsfootOption: D

B & D are both contenders for this scenario. I went with D because in the context of the scenario where regulatory requirements need to be implemented based on priority, "Dependency" would be the most appropriate choice. Because the priority of implementing regulatory requirements indicates a dependency relationship between the requirements themselves. Implementing a regulatory requirement may depend on the implementation of other related requirements or may necessitate the implementation of certain requirements before others. Therefore, using a "Dependency" relationship helps to identify the dependencies between different regulatory requirements and prioritize their implementation accordingly.

fepecyOption: B

Ans B, the relationship between a functional requirement (Regulatory req) and its corresponding solution components it satisfies.

YichunOption: D

Depends question content says "implement regulatory requirements". Regulatory requiremens should be necessity traceability relationship, which belongs to Depends, as stated in 5.1.4 Elements • Depends: relationship between two requirements, used when a requirement depends on another requirement. Types of dependency relationships include: • Necessity: when it only makes sense to implement a particular requirement if a related requirement is also implemented. • Effort: when a requirement is easier to implement if a related requirement is also implemented.