Question 97

What is a valid reason for prioritization?

    Correct Answer: B

    Effort and resources needed to implement a requirement is a valid reason for prioritization because understanding the cost in terms of effort and resources is crucial for making informed decisions. This information helps determine whether a requirement is feasible given the project's constraints and whether it provides a good return on investment. This kind of prioritization helps in optimizing the allocation of limited resources to achieve the best possible outcomes.

Discussion
Sourabh_SharmaOption: B

BABAOK V3 Pg 88 Cost: the effort and resources needed to implement the requirement. Information about cost typically comes from the implementation team or the vendor. Customers may change the priority of a requirement after learning the cost. Cost is often used in conjunction with other criteria, such as cost-benefit analysis.