Robert is the business analyst for his organization and he's working with several stakeholders to identify the business need for an opportunity. Robert needs to identify the stakeholder that will be responsible for authorizing the actions needed in order to meet the identified business need.

Which stakeholder does Robert need to identify?

    Correct Answer: A

    The stakeholder responsible for authorizing the actions needed to meet the identified business need is the Sponsor. The Sponsor is typically the person or group who provides the resources and support for the project and is accountable for enabling success. They have the authority to approve and fund the necessary actions to achieve the business goals.

Discussion
Dillon91Option: A

Correct..baokpg. 18