Exam CCBA All QuestionsBrowse all questions from this exam
Question 32

You are the business analyst for your organization. Your stakeholders have recently reviewed and approved the set of requirements that you've presented to them. You have now baselined the requirements. What does it mean to baseline the requirements in the light of this scenario? Choose the best answer.

    Correct Answer:

    Baselining the requirements means that the set of requirements has been reviewed and approved by stakeholders. Once baselined, any further changes to these requirements must go through a formal change control process. This ensures that changes are evaluated, approved, and documented properly to maintain project consistency and scope control.

Discussion
CheburaatorsOption: D

The baseline represents the approved requirements and any changes must go through a change control system.

Maddie88Option: D

The baseline represents the approved requirements and any changes must go through a change control system.

Surabhi_26Option: D

D is correct