CBAP Exam - Question 263


A business analyst (BA) is working on a stakeholder collaboration plan. The main goal is to select the approaches that work best to meet the needs of external and internal stakeholders.

Which aspects should be taken into account?

Show Answer
Correct Answer: C

When developing a stakeholder collaboration plan, it is crucial to consider the timing and frequency of collaboration. This ensures that the stakeholders' needs are met effectively and their interest and involvement are maintained throughout the initiative. Other aspects like the BA's collaboration skills, solution design, and business governance plan are important in different contexts but are not primary considerations for planning stakeholder engagement approaches.

Discussion

7 comments
Sign in to comment
cc2104Option: C
Aug 17, 2021

3.2.4.2 The business analyst may plan different collaboration approaches for internal and external stakeholders, and approaches may differ by business analysis activity. The objective is to select the approaches that work best to meet the needs of each stakeholder group and ensure their interest and involvement is maintained across the initiative. Some considerations when planning collaboration include: • timing and frequency of collaboration, • location, • available tools such as wikis and online communities, • delivery method such as in-person or virtual, and • preferences of the stakeholders.

rupakarthik
Mar 10, 2021

right ans

786NB786Option: C
Dec 8, 2021

C=Timing and frequency of collaboration

Dillon91Option: C
Jan 31, 2023

A: Define Stakeholder Collaboration Ensuring effective collaboration with stakeholders is essential for maintaining their engagement in business analysis activities. Collaboration can be a spontaneous event. However, much collaboration is deliberate and planned, with specific activities and outcomes determined ahead of time during planning activities. The business analyst may plan different collaboration approaches for internal and external stakeholders, and approaches may differ by business analysis activity. The objective is to select the approaches that work best to meet the needs of each stakeholder group and ensure their interest and involvement is maintained across the initiative. Some considerations when planning collaboration include: • timing and frequency of collaboration, • location, • available tools such as wikis and online communities, • delivery method such as in-person or virtual, and • preferences of the stakeholders

Dillon91Option: C
Feb 7, 2023

Actually C

NorieRoseOption: C
Jan 30, 2024

C. Timing and Frequency of Collaboration

Farooq_95Option: C
Apr 19, 2024

As per BABOK v3 3.2.4.2, the timing and frequency is one of the factor considered when planning collaboration.