Question 17

When can a change to requirements occur?

    Correct Answer: B

    A change to requirements can occur at any time during the project lifecycle. This flexibility ensures that the project can adapt to new information, feedback, or changes in business needs, which can happen at any stage from initial planning through execution and even after some testing has begun.

Discussion
Adnan8t2Option: B

ANSWER: B Page 91 – BABOK V3 Proposed Change: can be identified at any time and impact any aspect of business analysis work or deliverables completed to date.

HazemnzOption: B

BABOK page 91

ayoakinrindeOption: B

Page 91 – BABOK V3