In which requirements prioritization factor would time-to-market scenarios apply?
In which requirements prioritization factor would time-to-market scenarios apply?
Time sensitivity is directly related to time-to-market scenarios. When prioritizing requirements, if the project or product needs to be delivered within a specific timeframe to meet market demands, the time sensitivity factor will be a key consideration. Cost, stability, and regulatory or policy compliance focus on different aspects of the project that do not specifically address the urgency to reach the market quickly.
Babok page 88