Management would like you to front-load the requirements with the most risk requirements.
Why would management prefer the risky requirements first in the prioritization?
Management would like you to front-load the requirements with the most risk requirements.
Why would management prefer the risky requirements first in the prioritization?
Front-loading the requirements with the most risk requirements allows ample time to address and resolve any issues that arise from those risky requirements. This approach ensures that potential problems are identified and mitigated early in the project timeline, reducing the impact on the overall project and increasing the likelihood of successful completion.
The requirement that is most difficult to implement may be prioritized to the top of the list in order to minimize the resources that are spent before learning that a proposed solution can not be delivered
5.3.4 -If there is a risk that the solution is not technically feasible, the requirement that is most difficult to implement may be prioritized to the top of the list in order to minimize the resources that are spent before learning that a proposed solution cannot be delivered.