Exam CBAP All QuestionsBrowse all questions from this exam
Question 184

Which one of the following diagrams when properly laid out is always laid in a left to right display to properly reflect the chronology of all project work?

    Correct Answer: D

    A time-scaled schedule network diagram is always displayed left to right to properly reflect the chronology of all project work. It visually represents the project timeline and schedules tasks based on their respective times, ensuring the chronological order of activities is maintained.

Discussion
MFZZOption: B

I eventually agreed B as project schedules general work from left to right or may even loop to fill a missing gap

MFZZ

Is this even in BABOKv3?

ElyonSenjo

no, probably it's related to BABOK v2

NickManeOption: B

A, C - makes no sense D - scheduling activity, B - project scheduling, Correct