Which one of the following diagrams when properly laid out is always laid in a left to right display to properly reflect the chronology of all project work?
Which one of the following diagrams when properly laid out is always laid in a left to right display to properly reflect the chronology of all project work?
A time-scaled schedule network diagram is always displayed left to right to properly reflect the chronology of all project work. It visually represents the project timeline and schedules tasks based on their respective times, ensuring the chronological order of activities is maintained.
I eventually agreed B as project schedules general work from left to right or may even loop to fill a missing gap
Is this even in BABOKv3?
no, probably it's related to BABOK v2
A, C - makes no sense D - scheduling activity, B - project scheduling, Correct