Exam CBAP All QuestionsBrowse all questions from this exam
Question 9

You are the business analyst for your organization. Management has asked that you create a method to store the project requirements including those under development, under review, and the requirements which have been approved.

What is management asking you to create?

    Correct Answer: D

    Management is asking you to create a system to store all the project requirements, including those under development, under review, and those already approved. This system is typically referred to as a requirements register. A requirements register is a documented record of all requirements for a project, identified in various stages of their lifecycle, ensuring they are organized and managed effectively for easy access and reference.

Discussion
Dillon91Option: B

V3...p 45 ..answer is B

RabbitsfootOption: B

BABOK v3 pg 84 5.2.4 Elements .1 Maintain Requirements Requirements are maintained so that they remain correct and current after an approved change. Business analysts are responsible for conducting maintenance to ensure this level of accuracy is retained. For requirements to be properly maintained they must be clearly named and defined, and easily available to stakeholders. Business analysts also maintain the relationships among requirements, sets of requirements, and associated business analysis information to ensure the context and original intent of the requirement is preserved. Repositories with accepted taxonomies assist in establishing and maintaining links between maintained requirements, and facilitate requirements and designs traceability.

kal5Option: B

Page 45 BABOK V3. Repositorty