Question 182

Which of the following phases is the first step towards creating a business continuity plan?

    Correct Answer: B

    The first step towards creating a business continuity plan is 'Scope and Plan Initiation'. This phase involves defining the objectives, scope, and the basic framework for the project, which are essential before moving on to the creation and development of the actual plan. Without identifying the scope and initiating the plan, it would be impossible to develop a structured, effective business continuity plan.

Discussion
ElyonSenjoOption: B

BABOK v2

NkhemOption: B

@binu801 Every project starts with initiating a project plan with a scope

binu801Option: B

Any explanation on why B is the answer and not A