Question 181

____ is a process to determine the completeness of the project work and to gain the customer's acceptance to move the project forward.

    Correct Answer: C

    Verify scope is a process to ensure that the project deliverables are completed as agreed upon and to gain formal acceptance by the customer or stakeholder. It involves evaluating the project deliverables against the project scope to confirm that all work has been completed and meets the specified requirements. This process is essential for moving the project forward, as it provides assurance that the project work is complete and acceptable to the customer.

Discussion
AdeCBAPcertifiedOption: D

Quality Control is the answer.

ElyonSenjo

BABOK v2

OctavianGOption: C

The verify scope process secures formal acceptance of the completed project deliverables from the customer, end-user, or requesting party. Verifying scope includes reviewing the deliverables with the customer to ensure that they are completed satisfactorily in order to receive formal acceptance of the deliverables.

Sha7rourOption: C

Verify Scope is the only correct option: The primary purpose of the Verify Scope process is to formally accept completed deliverables and obtain sign-off that the deliverables are satisfactory and meet stakeholders' expectations. not from IIBA but PM -> https://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=&cad=rja&uact=8&ved=2ahUKEwifxOqQ-o78AhXdVKQEHfSjAyAQFnoECAwQAw&url=https%3A%2F%2Fwww.oreilly.com%2Flibrary%2Fview%2Fpmp-project-management%2F9780470479582%2F9780470479582_verify_scope.html%23%3A~%3Atext%3DThe%2520primary%2520purpose%2520of%2520the%2Cthe%2520acceptance%2520of%2520work%2520results.&usg=AOvVaw3DgCosCPJknXOrBr-PSdRp

binu801Option: C

Any explanations- How verify scope is related to completeness of project work