Exam CBAP All QuestionsBrowse all questions from this exam
Question 248

A business analyst (BA) is outlining who should participate in an upcoming requirements elicitation meeting.

From whom should the BA obtain approval before selecting the participants?

    Correct Answer: A

    The appropriate approval for selecting participants for a requirements elicitation meeting should be obtained from the sponsor. The sponsor has the authority to approve or deny a planned elicitation event and to authorize and require the participation of specific stakeholders. This ensures that the necessary stakeholders are involved as per the project's strategic objectives and overall governance.

Discussion
ObeeOption: A

Ans-A Sponsor: authorizes and ensures that the stakeholders necessary to participate in elicitation are involved(Babok Page 61). Note here, the key word here is authority(approval) and not just organising people and resources.

Kajol_2021Option: A

ANWER IS A • Project Manager: ensures that the appropriate people and resources are available to conduct the elicitation. • Sponsor: has the authority to approve or deny a planned elicitation event, and to authorize and require the participation of specific stakeholders.

rupakarthikOption: C

Ans-C Project Manager: ensures that the appropriate people and resources are available to conduct the elicitation.(BABOK Page-61)

GeocibeOption: C

Meaning of Ensure - make certain that (something) will occur or be the case// Project Manager: ensures that the appropriate people and resources are available to conduct the elicitation. • Sponsor: has the authority to approve or deny a planned elicitation event, and to authorize and require the participation of specific stakeholders // Sponsor only provides approval for "Specific stakeholders". The PM has the overall responsibility of seeing to it that the right stakeholders are available because they know who should be available.

RabbitsfootOption: A

BABOK 4.1.7 - • Project Manager: ensures that the appropriate people and resources are available to conduct the elicitation. • Sponsor: has the authority to approve or deny a planned elicitation event, and to authorize and require the participation of specific stakeholders.

MJeidahOption: A

Ans = A

ralphossaiOption: A

Sponsor is the right answer. Even the PM ensures he gets approval from the sponsor before any elicitation