You are the business analyst for your organization and you're working with several stakeholders to identify, manage, and approve requirements. Your organization requires using a plan-driven approach to business analysis and changing management. In this approach, who is most likely to approve changes to requirements?

    Correct Answer:

    In a plan-driven approach to business analysis and change management, the entity responsible for approving changes to requirements is typically the Change Control Board. This board is composed of managers, requirements owners, and key stakeholders who collectively review the change requests. They assess the validity, need, impact, and overall considerations of the proposed changes before deciding whether to approve or decline them. This structured and collective decision-making process ensures thorough evaluation and alignment with project goals.

Discussion
e4eswarrOption: B

Change control board is for change requests but this question is talking about requirements so shouldn't the answer be Requirement owners ?

CheburaatorsOption: A

Change control board