IIA-CIA-Part2 Exam - Question 129


Which of the following types of contracts would provide the least incentive for a contractor to achieve economy and efficiency?

Show Answer
Correct Answer: B

A cost-plus contract provides the least incentive for a contractor to achieve economy and efficiency. In this type of contract, the contractor is reimbursed for all allowable costs, plus an additional amount for profit. This can lead to inefficiency and higher costs since the contractor's profit is tied directly to the amount spent, offering little motivation to minimize expenses.

Discussion

2 comments
Sign in to comment
RenatocdoOption: D
Nov 28, 2023

O tipo de contrato que proporcionaria o menor incentivo para um contratante alcançar economia e eficiência é contrato de entrega por tempo indeterminado. Isso ocorre porque, em um contrato de entrega por tempo indeterminado, o contratante não tem nenhum incentivo financeiro para reduzir custos ou melhorar a eficiência, pois o preço é fixo e não depende do desempenho do contratante .

RenatocdoOption: B
Nov 28, 2023

Se o objetivo fosse fornecer o maior incentivo para um contratante alcançar economia e eficiência, o tipo de contrato mais apropriado seria contrato de custo-mais. Isso ocorre porque, em um contrato de custo-mais, o contratante é incentivado a reduzir custos e melhorar a eficiência, pois o preço final do contrato é baseado nos custos reais incorridos pelo contratante, além de uma taxa fixa de lucro .