IIA-CIA-Part3 Exam QuestionsBrowse all questions from this exam

IIA-CIA-Part3 Exam - Question 158


At what stage of project integration management would a project manager and project management team typically coordinate the various technical and organizational interfaces that exist in the project?

Show Answer
Correct Answer: AB

During project plan execution, the project manager and project management team coordinate the various technical and organizational interfaces that exist in the project. This stage involves implementing the project plan and ensuring that the different aspects of the project are integrated and functioning together as planned. This requires coordination with various stakeholders and departments to manage project activities effectively and efficiently.

Discussion

1 comment
Sign in to comment
ElvinOption: B
Feb 29, 2024

why not b?

Elvin
Mar 6, 2024

I'm thinking B because during this stage, the project manager and team work on putting the project plan into action by executing the tasks and activities outlined in the plan. This involves coordinating with different stakeholders, including technical experts and other departments, to ensure that the project progresses smoothly.

KonradK
Mar 11, 2024

Agree with you here