Exam IIA-CIA-Part2 All QuestionsBrowse all questions from this exam
Question 72

All of the following tools are employed to control large-scale projects except:

    Correct Answer: C

    Statistical process control is a method used in quality management to monitor and control processes using statistical methods. It is not used specifically for managing or controlling large-scale projects. Program evaluation and review technique (PERT), Critical path method, and Gantt charts are all specifically designed for project management and control.

Discussion
NangamsoOption: C

Statistical process control is a method of quality control which employs statistical methods to monitor and control a process - it is not a project management tools like A, B and D

KonradK

Could someone please provide the explanation?