An organization was forced to stop production unexpectedly, as raw materials could not be delivered due to a military conflict in the region. Which of the following plans have most likely failed to support the organization?
An organization was forced to stop production unexpectedly, as raw materials could not be delivered due to a military conflict in the region. Which of the following plans have most likely failed to support the organization?
Contingency plans are designed to deal with unexpected disruptions or emergencies, such as a military conflict affecting the delivery of raw materials. These plans include alternative strategies and actions to ensure continuity of operations despite unforeseen events. The failure to have a contingency plan in place indicates that the organization was not prepared to handle this kind of situation.
I read the question in a wrong way... A IS CORRECT
Shouldn't it be C for contingency plans as military conflict impacted delivery of materials