IIA-CIA-Part3 Exam - Question 30


The internal audit activity completed an initial risk analysis of the organization's data storage center and found several areas of concern. Which of the following is the most appropriate next step?

Show Answer
Correct Answer: D

Once an initial risk analysis has identified several areas of concern, the next appropriate step is to conduct a risk assessment. Risk assessment involves evaluating the identified risks to determine their potential impact and likelihood, which helps in prioritizing them for response. This step ensures that the organization understands which risks are most critical and require immediate action or further analysis.

Discussion

3 comments
Sign in to comment
Java_GirlOption: D
Jul 27, 2021

after risks were identified, this risk needs to be assessed level (high, medium or low)

khashah
Apr 4, 2021

Why D plz explain

[Removed]
Sep 8, 2023

could you please write correct order of full steps?