Exam IIA-CIA-Part3 All QuestionsBrowse all questions from this exam
Question 92

With regard to disaster recovery planning, which of the following would most likely involve stakeholders from several departments?

    Correct Answer: B

    Prioritizing the order in which business systems would be restored would most likely involve stakeholders from several departments. This process requires input from various departments to determine which systems are most critical to the organization’s operations and should be restored first. Each department may have different priorities and needs, and a collaborative approach ensures that the organization recovers in a way that minimizes disruption and supports business continuity.

Discussion
KelimeOption: B

B. Prioritizing the order in which business systems would be restored.Assessing the resources needed to meet the data recovery objectives in disaster recovery planning is important, but prioritizing the order of restoring business systems would most likely involve stakeholders from several departments, as it requires coordination and input from various parts of the organization.

ciacandidateOption: B

B is correct. Because it is not necessary to involve multiple stakeholders to assess resources needed to meet data recovery objectives. The stakeholders would be involved to prioritize, not assessing. Otherwise, these stakeholders should be doing the disaster recovery planning, instead of the specialist.

TicoOption: D

I thought A or D. Why A is inappropriate?

Ren_92

A is similar to B which both doesn't require extensive labor and could go away with few key people at the top unlike D