IIA-CIA-Part1 Exam QuestionsBrowse all questions from this exam

IIA-CIA-Part1 Exam - Question 71


Due to urgent requests from management, a busy internal audit activity finds that it can no longer meet all of its commitments contained in the annual audit plan.

The best course of action for the chief audit executive to take would be to:

Show Answer
Correct Answer: C

The chief audit executive should advise both the board and senior management to ensure that all stakeholders are aware of the situation. Requesting a reassessment of the audit plan allows for a comprehensive review of priorities and resources, ensuring that the most critical and high-risk areas are addressed first. This approach ensures that the internal audit function remains aligned with the organization's overall objectives and risk management strategy.

Discussion

4 comments
Sign in to comment
NadiaDOption: C
Feb 14, 2021

Audit plan re-assessment is the answer because sometimes organization does not have any budget/money to allocate additional resources.

Pal_kiOption: D
Nov 24, 2020

why not D ?

nehabhineetOption: D
Jan 10, 2021

correct, it should be D

John1237Option: C
May 22, 2022

Option B would have been the ideal approach (taking into account the risks), if the Board of Directors was also informed. Option C is appropriate and implies that the advice provided will take into account the risk-based approach.