Question 86

A company has an asset that has failed and an administrator needs to create a work plan that includes exact steps and descriptions that need to be followed to get the asset in operating status. Which option does the administrator need to follow?

    Correct Answer: D

    To address an asset that has failed and requires precise instructions to return it to operating status, the administrator should create a work order, add tasks, and populate the summary field. This approach ensures that all necessary steps and descriptions are clearly outlined and assigned as tasks within the work order, providing a detailed and structured plan for the repair or maintenance work required.

Discussion
tomben_euOption: A

I think answer is A: Work process flows use relationships between work orders and tasks to automate the flow of status changes. You set relationships between work orders and tasks so that when a task is completed, the next task in the flow can be initiated. https://www.ibm.com/support/knowledgecenter/en/SSLKT6_7.6.1.2/com.ibm.mbs.doc/mbs_common/t_defining_flow_actions.html?pos=6