Exam C2010-555 All QuestionsBrowse all questions from this exam
Question 57

A company wishes to configure Maximo so that meter readings automatically create work orders based on condition monitoring points. The company has already configured the system in Organizational settings and created the appropriate condition monitoring points.

What additionally needs to be configured for this be accomplish?

    Correct Answer: C

    To configure Maximo so that meter readings automatically create work orders based on condition monitoring points, a gauge type meter should be added to an asset and the MeasurePointWoGenCronTask should be active. Gauge meters are typically used in condition monitoring because they measure variables such as pressure, temperature, or flow rate, which are critical for determining asset condition.

Discussion
marcoagbOption: C

right answer is C https://www.ibm.com/support/pages/setting-measure-point-wogen-crontask

SSABRAOption: C

Correct answer is C

elma93Option: B

Answer is B, Continuous meter is cumulative.

Lavoisier

No the correct answer is C. Continuous meter can't be use with condition monitoring