The organizational rules allow for labor hours entered by internal laborers to be automatically approved. An internal laborer records 44 hours of actual labor when only 4 hours were completed.
How can this be corrected?
The organizational rules allow for labor hours entered by internal laborers to be automatically approved. An internal laborer records 44 hours of actual labor when only 4 hours were completed.
How can this be corrected?
The correct way to correct the recorded hours is by editing the entry using the Labor Reporting application. This allows for precise correction of the incorrectly reported hours without the need for additional labor transactions or creating duplicate entries. By using the Labor Reporting application, you maintain accurate and proper documentation of labor records.
https://www.ibm.com/support/pages/correcting-labor-hours-after-labor-approved
C is the COrrect as After Approve Actual Labor Hour No Edit or Modify so using Negative hour with Same Labor and Same Date of Actual