Question 17

A maintenance planner is in the process of planning time sensitive emergency maintenance work orders for a number of assets where items need to be reserved.

What reservation type should be used?

    Correct Answer: B

    When planning time-sensitive emergency maintenance work orders that require items to be reserved, a 'Hard' reservation should be used. A hard reservation ensures that materials are specifically allocated to the work order, preventing them from being used for any other purpose. This is crucial in emergency situations where timely access to the appropriate resources is essential for effective maintenance.

Discussion
fdeghadiOption: B

this Will require hard reservation not soft so material issue first to that sensitive Work ORder Job