Exam C2010-555 All QuestionsBrowse all questions from this exam
Question 29

A company wants to trigger a PM based on a characteristic type meter.

How can this be accomplished?

    Correct Answer: C

    To trigger a Preventive Maintenance (PM) based on a characteristic type meter, the correct approach is to create a PM against the asset and specify the meter on the Frequency tab of the PM. This ensures the PM is appropriately triggered based on meter readings linked to the asset, aligning with the standard procedures for condition-based maintenance.

Discussion
fdeghadiOption: B

B is the correct as Guage and Char meter is only applicable with Cond montoring PM is used only with continuous meter for (Time-meter) base

dlpOption: B

The answer is B. Meters do not check for characteristics. Condition Monitoring does.

Gusagrom

I agree.

Sindhu_TyroOption: C

I think answer is C

khadija_lassouedOption: C

https://www.ibm.com/docs/en/mam/7.6.0?topic=application-preventive-maintenance-frequency-schedules B is wrong we specify a value not a limit with Characteristic Meter https://www.ibm.com/support/pages/node/100591?mhsrc=ibmsearch_a&mhq=condition%20monitoring%20characteristic%20type%20meter