Exam C2010-555 All QuestionsBrowse all questions from this exam
Question 85

A company wants to receive rotating items that require inspection. What is the order of tasks necessary to do this?

    Correct Answer: D

    The correct order of tasks necessary for a company to receive rotating items that require inspection is to first receive the rotating items, then assign an asset number, and finally change the inspection status. Receiving the items is the initial step to acknowledge their arrival, assigning an asset number is required to track them within the system, and finally, changing the inspection status confirms that the items have been inspected. This sequence ensures that the items are properly logged, tracked, and verified.

Discussion
VaheeOption: B

answer is B

rasmagao

https://www.ibm.com/support/pages/receiving-rotating-items-maximo

ps_777Option: A

Answer is A https://www.ibm.com/support/knowledgecenter/SSFGJ4_7.6.0/com.ibm.mbs.doc/receipts/t_receive_material_rotate.html

maxbossOption: B

B is correct. WISP, Change inspection status, WASSET, assign asset#, Receive Rotating Items

aismail7000Option: A

Answer is A

YiorgosOption: B

The only possible answer is B The rotating item requires inspection as per the question. The Change Inspection Status action must be before Receive Rotating Items action for the items to appear.