A company is using Process Flow Control and wants to change the default values for Flow Start and Flow Complete statuses.

Where can these values be configured?

Show Answer
Correct Answer: B

The default values for Flow Start and Flow Complete statuses can be configured in the Work Type settings. By selecting Work Order Options followed by Work Type, you can specify the values for the start status and the complete status.

Discussion

2 comments
Sign in to comment
everwelwisherOption: B
Aug 13, 2021

B is correct

arexaeiramOption: B
Aug 27, 2023

B is correct. by selecting Work Order Options > Work Type and specifying values for the start status and the complete status. https://www.ibm.com/docs/en/control-desk/7.6.0.2?topic=orders-work-order-statuses