An administrator want to create a time based escalation point to evaluate to 30 days in the future.
What is the correct value to use in the Elapsed Time Interval field along with the Elapsed Time Attribute?
An administrator want to create a time based escalation point to evaluate to 30 days in the future.
What is the correct value to use in the Elapsed Time Interval field along with the Elapsed Time Attribute?
To create a time-based escalation point evaluating 30 days in the future, it is necessary to use a negative value in the Elapsed Time Interval field to indicate the future period. Therefore, the correct value to use is -30.
Answer should be D. -30 https://www.ibm.com/support/knowledgecenter/SSBLW8/com.ibm.mbs.doc/escalation/t_defining_escalation_pts.html
Answer D
the correct is D as A negative time period for future
Answer D