Question 52

In which status can a Job Plan be modified to add a new task?

    Correct Answer: D

    A Job Plan can be modified to add a new task when it is in the PNDREV (Pending Review) status. This status allows for changes and updates to be made before the Job Plan becomes active or is applied to work orders.

Discussion
ddmann999Option: D

Answer is D

VijiyOption: D

Correct Answer is D. Verified in Maximo