A company has a work order with 50 separate tasks and 40 of the tasks have been completed. The company would like the remaining 10 tasks grouped with a new parent work order.

Which option will group the tasks?

    Correct Answer: D

    To group the remaining 10 tasks with a new parent work order, you should create a new work order and add the child work orders on the Plans tab. This will ensure that the 10 remaining tasks are properly organized under the new parent work order.