Exam C2010-555 All QuestionsBrowse all questions from this exam
Question 63

A supervisor has a requirement in Labor Reporting to report labor hours for work that has been completed.

What are the options available to report labor?

    Correct Answer: B

    To report labor hours for work that has been completed, the available options are labor, crew, vendor/contract, work order, and ticket. These options comprehensively cover different aspects necessary for accurately recording the labor involved in various scenarios, including individual labor reporting, crew-based reporting, vendor/contract-based reporting, and work order-specific reporting as well as ticket-based for specific instances.

Discussion
rasmagaoOption: B

Answer is B You can record daily attendance when you specify labor transactions by work order, by ticket, by crew, by labor, or by contract/vendor

everwelwisherOption: B

correct Answer is B