Exam C1000-132 All QuestionsBrowse all questions from this exam
Question 21

A user wishes to perform the same work tasks on several assets simultaneously. How can this be configured?

    Correct Answer: D

    To perform the same work tasks on several assets simultaneously, the Assets should be specified on the Multiple Assets, Locations and CIs table on the Work Order. This allows for the task to be applied concurrently across all specified assets, which meets the requirement of simultaneous execution.

Discussion
StfanOption: D

I would opt for D. As the question says *simultaneously*, therefor the Multi Asset, Loc, CI table suffices. Adding them to a route as mentioned in Answer A, may result in either Child WO's, Tasks or Multi Asset Location CI table anyway.

SSABRAOption: D

Correct answer is D.