C1000-132 Exam - Question 21


A user wishes to perform the same work tasks on several assets simultaneously. How can this be configured?

Show Answer
Correct Answer: D

To perform the same work tasks on several assets simultaneously, the Assets should be specified on the Multiple Assets, Locations and CIs table on the Work Order. This allows for the task to be applied concurrently across all specified assets, which meets the requirement of simultaneous execution.

Discussion

2 comments
Sign in to comment
StfanOption: D
Jan 23, 2024

I would opt for D. As the question says *simultaneously*, therefor the Multi Asset, Loc, CI table suffices. Adding them to a route as mentioned in Answer A, may result in either Child WO's, Tasks or Multi Asset Location CI table anyway.

SSABRAOption: D
Mar 4, 2024

Correct answer is D.